Luguang Electronics Advanced Semiconductor Industry Park Capping Test

Luguang Electronics Advanced Semiconductor Industry Park Capping Test


On July 15, 2021, the scheduling meeting for the construction of the Luguang Electronics Advanced Semiconductor Packaging and Testing Industrial Park was urgently held.

 Luguang Electronics Advanced Semiconductor Industry Park Capping Test

Since the construction of the second phase of Luguang Electronics Industrial Park started on April 20th, it has attracted widespread attention and support from governments at all levels. Currently, the construction has entered the critical period of pouring the third floor, and a comprehensive report has been made on the progress since the start of construction. And take measures to correct and improve any deficiencies that arise during the construction process. With the arrival of the rainy season, it is even more important to strengthen safety production. While ensuring safety, we should focus on quality and promote production, ensuring that the roof is completed and enters the decoration stage by August 10th. We strive to complete the construction and put it into use by December 1st.

 Luguang Electronics Advanced Semiconductor Industry Park Capping Test

The meeting was summarized and delivered by Zhu Ligui, the Chairman of the Construction Unit of Luguang Electronics, who affirmed the preliminary work of the four units involved in the construction, gave high praise to Mr. Ge of Chunhui Installation Engineering, put forward higher requirements for project construction, and made strict requirements for safety operations. The four parties reached an agreement on the current work progress and successfully completed the construction task of Luguang Electronics Advanced Semiconductor Packaging Industrial Park with practical actions.

The completion of the main body of the Luguang Electronics 5G Communication Semiconductor Packaging and Testing Industrial Park and the Third Generation Semiconductor Industrial Park